October 21, 2025
VCC Construction Services
4600 West Cypress Street, Suite 460
Tampa, FL 33607
Attn: Nathan Youngblood, Project Manager
O: 813-331-8032
C: 813-538-5348
nyoungblood@vccusa.com
Plumbing SCOPE OF WORK
Remote Meter installation labor is included in all buildings.
Fixtures, Accessories, and Drains
Bldg 100 WF
3 AD-1
3 FCO
4 HB
1
5
TD-1
COTG
Bldg 150
2 COTG
12 FCO
3 HB-1
Bldg 200
3 COTG
10 FCO
5 HB-1
Bldg 300
3 COTG
10 FCO
4 HB-1
Materials
All DWV piping to be SCH 40 PVC pipe and fittings.
All Water piping to be copper pipe and fittings.
Exclusions
Grease traps (add see below)
Any Seismic restraints
Any dewatering
Demolition work.
Composite Labor, Broom sweep of floors & Dumpster charges.
Drywall access doors for ceilings or walls.
Housekeeping pads (By others).
Concrete cutting & coring, removal &.
Protection of Materials & Equipment following installation.
Asbestos Work of any kind.
Ceiling removal or replacement, or repair of grid.
Fireproofing repairs or back charges.
Structural & Supplemental Steel framing, and Platforms.
X-ray of floor slabs or roof deck.
Painting of mechanical and plumbing systems (By others).
Roofing work or cutting of roof.
LEEDS certification excluded.
Buy America Act domestic requirement.
Davis Bacon Wages Federal wage.
Bond is excluded if needed add 2%.
Overtime, premium time, & shift work.
Whole Foods Shell
$50,000
BLDG 150
$50,000
BLDG 200
$50,000
BLDG 300
$50,000
(1) - 1,500 Grease Trap Complete Install
$50,000
Alt Add Allowance for (3)-Badger remote read meters-(No Spec’s)
$50,000