September 8, 2025

Fulcrum Construction
1945 The Exchange SE, Suite 400
Atlanta, GA 30339

Job: PGA Superstore
St. Petersburg, FL

Attn: Kurtis Davis
310-339-9477
kdavis@fulcrumconstruction.com

Plumbing SCOPE OF WORK - Revision B

2 WC1 Water Closets Kohler with seat and supplies.
4 WC2 ADA Water Closets Kohler with seat and supplies.
4 LAV1 ADA Lavatories Sink by others. Faucet by plumber.
4 LAV2 ADA Lavatories Kohler with faucet and supplies.
2 UR Urinals Kohler with flush valve and supplies.
1 EWC ADA Electric Water Cooler Elkay EZSTL8WSLK.
1 MS Mop Sink Fiat MSBID2424100.
3 FD Floor Drains Zurn ZN415-3NH-5S-P.
2 HB Hose Bibbs Zurn Z1345-06.
2 IMB Ice Maker Boxes Mainline ML11449.
1 KS ADA Kitchen Sink Elkay ELUHAD211545.
1 S1 Service Sink Elkay LRAD202265PD3.
2 FCO Floor Cleanouts Zurn ZB1400-4NH-VP.
4 WCO Wall Cleanouts Zurn Z1445-3NH-BP.
1 SP-1 Sewage Pump Liberty P382PRD101SD.
1 WH-1 Water Heater Rheem ELD40-FTB, 40-gallon.
1 WH-2 Water Heater Rheem EGSP10, 10-gallon.
1 IWH Instantaneous Tankless Eemax SPEX4208.
1 Air Compressor CAT-4610AC #43NU29.
1 Hose Reel Klutch #49588.
1 Vacuum Pump JDC-501.
2 Flex Hoses Jet 414730.

Material

All waste and vent piping to be SCH 40 PVC pipe and fittings.
All water piping to be CPVC pipe and fittings.
All water piping to be Armaflex insulated.

Conditions

Any permits and/or fees to be paid by others. Price is good for 30 days. After 30 days, if our prices increase, we will increase yours accordingly. Upon receiving a Letter of Intent, contract to follow within 15 days, to hold pricing. Price reflects work to be done Monday – Friday 7:00am – 3:30pm. No additional work to be performed without an approved change order. Any breaking and/or patching of floors or walls are not included in this scope of work. Removal of excess excavation materials of any type is not included in this scope of work. Water, quicksand, rock, environmental contamination, asbestos, or other unforeseen obstructions or subsurface soil conditions will constitute conditions above and beyond this scope of work. Additional cost in forementioned conditions shall be agreed upon in writing between Brighter Utilities Tampa Plumbing LLC dba B&B Professional Plumbing and Air and the General Contractor.

Late Payments

Payments are to be made in monthly draws within 29 days of each monthly request. In the event any payments are not made when due, including final payment, the General Contractor shall be liable for interest in an amount to 1.5% per month or the maximum legal rate permitted by law, accruing from the date the last payment became overdue.

Total Contract Price

SIXTY-SIX THOUSAND TWO HUNDRED FIFTY DOLLARS AND NO/100

$66,250.00

Respectfully,

Tim Mitchell
Project Manager
tim@bbproplumbing.com

 

Managed By Cassus Media