Beall's Outlet (Wesley Chapel)
Plumbing & HVAC Project
Location: 6105 Wesley Grove Blvd, Wesley Chapel Fl 33544
Completion Date: 6/08/2022
HVAC Scope of Work:
HVAC SYSTEMS: Service 5 existing RTU’s and change filters. Install owner furnished thermostat replacement.
EXHAUST FANS: Furnish and Install (3) ceiling exhaust fans. Install (1) louver and (16) pieces of air distribution.
DUCTWORK: Supply and install rectangle ductwork and snap lock with 2” wrap. Add smoke detectors to supply drops.
INSTALLATION AND PERMITS: Complete installation of the HVAC system by experienced, non-union workmen. Supervision and inspection are included.
START-UP and AIR BALANCE: Start up to be done by B&B Professional Plumbing and Air. A certified Air-Balance by an independent 3rd party is included.
Scope of Work:
-
Water Cooler
-
Wall Hung Lavatory
-
Lavatory
-
Electric Water Cooler
-
Mop Sink
-
Counter Sink
-
Floor Drain
-
Trap Primer
-
Electric Water Heater
-
Water Hammer Arrestors
-
Vacuum Breakers
-
Recirc. Pump
-
Grade Clean Out
-
Wall Clean Out